Thar Coal Mine set for full-scale operations with approved tariff

The tariff was set at $36.70 per tonne
The image shows Thar Coal mining. Photo via AFP
The image shows Thar Coal mining. Photo via AFP

Pakistan’s Thar Coal Block-II mine is poised for full-scale operations following the approval of its Commercial Operations Date (COD) Stage tariff by the Thar Coal & Energy Board (TCEB).

The TCEB, chaired by the Sindh Chief Minister, unanimously approved the COD Stage tariff for the mine’s Phase-II, which boasts a capacity of 7.6 million tonnes per annum (Mtpa).

The tariff was set at $36.70 per tonne, significantly lower than the initially proposed $45.80 per tonne.

The Thar Coalfield aims to reduce energy tariff prices across the nation, and the implementation of these projects is expected to bring tangible benefits to both the region and the nation as a whole.

Read more

Rangers truck meets accident in Thar, 2 officials killed

Liberty confident its $125m bet on troubled power sector will reap reward

PM orders linking of Thar Coal Mines with railway network by March next year

The TCEB also sanctioned revised financing terms for the review Contract Stage tariff of Thar coal Block-II mine, Phase-III.

This phase has an enhanced capacity of 11.2 Mtpa, and the approved terms include an increase in the lending spread to up to 1.85% over the benchmark interest rate.

For the latest news, follow us on Twitter @Aaj_Urdu. We are also on Facebook, Instagram and YouTube.

Thar Coal Mine

full Scale operations

Commercial Operations Date

Thar Coal & Energy Board